Sovereign Court – Hammersmith

  • Sector – Mixed Use
  • Scope –
    • Traffic marshalling
    • Working at height using a MEWP
    • Targeted opening up works of the façade
    • Intrusive FRAEW inspections
    • Careful reinstatement of the façade
  • Duration – 2 weeks for 5 operatives

Key Challenges:

  • Working at height in a live environment
  • Coordinating traffic management with required permits
  • Road closures while maintaining safe pedestrian access
  • Use of pedestrian marshals to ensure public safety

Categories

Clients:

N/a

Category:

Focused FRAEW Investigations

Date:

April 2026